FCC & CE for Wireless Products
FCC & CE for Wireless Products: The Test Plan Before the Lab
An intentional radiator must be certified by a Telecommunication Certification Body before it can be marketed in the US, and the module path narrows the obligation to Subpart B testing at $3,000–$8,000 in 2–6 weeks, against $18,000–$58,000 and 8–16 weeks for a custom radio. The module's authorisation evaporates the moment any tested condition is modified, and the base forfeiture for marketing unauthorised equipment is $7,000 per model. The test plan, the costs, and the Example Labs hub's module-vs-custom arithmetic.
Picture the hardware founder whose wireless product is ready to ship and is not legally sellable. The lab failed it, and the retest is six weeks away. The quote is double the budget, because the launch date assumed certification was a checkbox, a form to fill in, a fee to pay, a mark to stick on.
Or the product shipped, and the letter arrived: the device was marketed without the required authorisation, and the base forfeiture is $7,000 per model. The founder's mistake was not the radio. It was the assumption that certification is the last step.
It is the first decision, module or custom radio, and it is made at the schematic, not at the lab, because the module path and the custom path differ by $15,000 to $50,000 and by 3 to 18 weeks, and the difference is decided by the antenna, the enclosure, and the ground plane the founder chose months before the lab ever saw the board.
Example Labs is a made-up company we use for worked examples.
Certification is not a test. It is a legal condition for selling the product, and the test is the evidence behind it. This article is the test plan before the lab: the law in the US and the EU, the module path and what it does and does not cover, the costs and the timelines with the sources that disagree about them, the real numbers from a module that actually went through it, the fine, and the Example Labs hub's module-versus-custom arithmetic, the break-even volume, the launch delay, and the conditions that evaporate the authorisation.
The words, in plain English
Intentional radiator. A device designed to transmit radio frequency energy, Wi-Fi, Bluetooth, LTE, Zigbee, a remote control, a garage door opener. If the product's core function depends on broadcasting a radio signal to reach another device, it is an intentional radiator, and it falls under Part 15 Subpart C.
Unintentional radiator. A device that makes radio frequency energy for use inside itself but is not meant to emit it, the digital circuitry in every product, the clock, the processor, the switching converter. It falls under Part 15 Subpart B, and it is the part the host still owns even when the radio is a pre-certified module.
Certification. The FCC's equipment authorisation for intentional radiators: testing at an accredited laboratory, a technical documentation package reviewed against 47 CFR Part 15, and a grant of equipment authorisation issued by a Telecommunication Certification Body (TCB). The grant produces an FCC ID that must appear on the device.
SDoC (Supplier's Declaration of Conformity). The self-declaration path for unintentional radiators: the manufacturer pays a lab to measure the product's emissions against the Subpart B limits, keeps the test report and supporting documents on file, includes a compliance statement with the product, and is done. No TCB, no FCC ID.
TCB (Telecommunication Certification Body). An accredited body that reviews the test report and the documentation and issues the grant. The lab tests; the TCB grants.
Module / modular transmitter. A completely self-contained radiofrequency transmitter device, typically incorporated into another product, the radio chip, the crystal, the RF circuitry, and often the antenna, on a small shielded board that already has its own FCC ID. A single module has its own shielding, buffered modulation and data inputs, its own power supply regulation, and a permanently attached antenna or a unique antenna connector.
Limited modular approval (LMA). A module approval granted when not all eight criteria can be met, restricted to a host or an environment in which the module can satisfy them.
Grant. The certification the TCB issues. A grant of certification is valid only when the device is labelled in accordance with the rules, and it recognises that the equipment has been shown to be capable of compliance if no unauthorised change is made in the equipment and if the equipment is properly maintained and operated (§2.927).
Permissive change. A change to certificated equipment that may be made without a new application, under §2.1043. Anything else, any change in the design, circuitry, or construction, requires a new application for an equipment authorisation (§2.932).
RED (Radio Equipment Directive 2014/53/EU). The EU directive for wireless devices: radio, EMC, safety, and (since August 2025) cybersecurity, in one directive. CE marking is the manufacturer's own declaration that the product meets the law, not a certification issued by a testing house, and the technical file is the evidence behind it.
Harmonised standard. A standard the EU has listed as giving a presumption of conformity with a directive, EN 300 328 for a 2.4 GHz radio, EN 55032 and EN 55035 for EMC, EN 62368-1 for safety, EN 18031 for cybersecurity. Testing to the harmonised standard is the usual way to show the product meets the directive.
Class A / Class B. The two sets of emissions limits. Class A is for devices marketed for commercial or industrial use. Class B is the stricter set, for devices marketed for use in a residential environment, which is to say, most products. If a consumer can buy it, plan on Class B.
The law in the US: §15.201, and what it does not cover
The rule is one sentence, and it is the sentence the whole article hangs on. From the eCFR text of 47 CFR §15.201: except as otherwise exempted, all intentional radiators operating under the provisions of this part shall be certified by the Telecommunication Certification Bodies pursuant to the procedures in subpart J of part 2 of this chapter prior to marketing. Before marketing, not before shipping, not before the first customer, before the product is advertised or sold in the US.
The grant produces an FCC ID that must appear on the device, and the device must carry a specific compliance statement.
The exceptions are narrow, and they are worth naming because they are the only way out of certification. Under §15.201(a): intentional radiators operated as carrier current systems, devices operated under §§15.211, 15.213, and 15.221, and devices operating below 490 kHz in which all emissions are at least 40 dB below the limits in §15.209, those are subject to SDoC instead. Everything else that intentionally transmits is certified, or it is not marketed.
Every Part 15 device operates under two conditions, from §15.19, which later appear verbatim on the product's label: it must not cause harmful interference to other radio users, and it must accept any interference it receives, including interference that causes undesired operation. The antenna is restricted too, by §15.203: the device must be built so that no antenna other than the one supplied by the manufacturer can be used, a permanently attached antenna, or a unique coupling mechanism. Standard antenna jacks and common electrical connectors are prohibited.
And the host still owns Subpart B. A granted radio module settles the intentional radiator, Subpart C, but the finished product's digital circuitry is an unintentional radiator under Subpart B and still needs authorisation. The host manufacturer is responsible for ensuring that compliance, and the module's grant does not remove it.
A product with no radio at all is on the SDoC path: a lab measures its emissions against the Subpart B limits, the manufacturer keeps the report on file, and includes a compliance statement with the product. A product with a radio is on both paths at once, the module's certification for the radio, and the host's own authorisation for everything else.
The module path
The module path is 47 CFR §15.212, and it is the most operationally important route for a hardware startup. A pre-certified module, an ESP32, a Nordic nRF series chip, a Sierra Wireless modem, already holds its own FCC ID, and the host inherits the radio function, provided the tested conditions are preserved. The eight criteria for a single modular transmitter are the conditions, and they are worth reading as a checklist, because each one is a thing the host can break:
- The radio elements must have the radio frequency circuitry shielded. Physical components and tuning capacitors may be located external to the shield, but must be on the module assembly.
- The module must have buffered modulation and data inputs, to ensure the device will comply with Part 15 requirements with any type of input signal.
- The module must contain power supply regulation on the module.
- The module must contain a permanently attached antenna, or a unique antenna connector, and be marketed and operated only with specific antennas, per §§15.203, 15.204(b), 15.204(c), 15.212(a), and 2.929(b).
- The module must demonstrate compliance in a standalone configuration.
- The module must be labelled with its permanently affixed FCC ID label, or use an electronic display.
- The module must comply with all specific rules applicable to the transmitter, including all the conditions provided in the integration instructions by the grantee.
- The module must comply with RF exposure requirements.
If the FCC ID of the module is labelled on the host system, additional authorisation is not needed outside of radiated emissions and RF exposure (SAR), as long as those conditions hold. The host must follow the module's grant conditions, including its approved antenna, and the rest of the product may have obligations of its own. A module approval does not automatically cover the finished product.
The authorisation evaporates the moment any tested condition is modified. §2.927 says the grant recognises compliance only if no unauthorised change is made in the equipment. §2.932 says a new application for an equipment authorisation shall be filed whenever there is a change in the design, circuitry, or construction of a device for which an authorisation has been issued, except for permissive changes under §2.1043. Change the antenna, change the enclosure in a way that changes the antenna's environment, change the firmware's transmit power or duty cycle, and the module's grant no longer covers the host.
The #34 piece is the reason: the ground plane is the counterpoise, the other half of the dipole, and shrinking or crowding it has changed the antenna, not merely its surroundings; the keep-out is a copper-free zone on every layer beneath and around the radiating element; a metal enclosure moves a printed antenna by more than 40 MHz and degrades its return loss from −15 dB to −6 dB. The antenna the module was tested with is the antenna the host must use, in the environment it was tested in, and the #35 piece's enclosure is the same warning from the thermal side: the heatsink's ambient is the inside air, and the antenna's environment is the inside of the box.
The law in the EU: the RED, and what it adds
CE for wireless devices is the Radio Equipment Directive 2014/53/EU, radio, EMC, and safety in one directive, and since August 2025, cybersecurity as well. The core tests are EMC to EN 55032 (emissions) and EN 55035 (immunity), safety to EN 62368-1, and the radio to the ETSI standard for the band, EN 300 328 for a 2.4 GHz wideband radio, EN 301 893 for 5 GHz. The SparkFun Artemis module's CE RED test used EN 300 328 v2.1.1, EN 301 489-1 v1.9.2 and EN 301 489-17 v3.2.0, and EN 62479:2010, and its CE LVD test used IEC 62368-1:2014.
The difference from the US is the shape of the obligation. CE marking is the manufacturer's own declaration, not a certification issued by a testing house; the technical file is the evidence behind it, and the EU charges no fee for the mark itself. The FCC tests only what the device emits, it does not test what the device can withstand, and it does not cover electrical safety, which is a separate UL/NRTL process.
The EU requires immunity testing (the IEC 61000-4-x series) and integrates safety through the Low Voltage Directive. And since 1 August 2025, the RED's cybersecurity requirements apply, Article 3(3)(d), (e), and (f), under Delegated Regulation (EU) 2022/30, assessed to EN 18031, for radio equipment that connects to the internet, processes personal data, or handles payments. The #15 piece's version is the same: wireless (RED) testing runs €1,500–€3,000+ plus the EN 18031 cybersecurity assessment, from one provider's 2026 guide, labelled as such.
The adjacent framework is the Machinery Regulation, from #15: Regulation (EU) 2023/1230 applies on Wednesday 20 January 2027, repealing Directive 2006/42/EC, with a hard cut-over for machines placed on the market from that date and no grace period. A wireless product that is also a machine, a cobot, a robot arm, a machine with a radio in it, has to meet both frameworks, and the radio's RED file and the machine's technical file are two files, not one.
The costs, the timelines, and the sources that disagree
The module path narrows the obligation to Part 15 Subpart B unintentional-radiator testing, which costs $3,000–$8,000 and takes 2–6 weeks. A custom radio design certification typically runs $18,000–$58,000 and takes 8–16 weeks for lab testing alone, with the full end-to-end timeline, pre-compliance testing, formal lab submission, and TCB grant, running 9–20 weeks (Promise Legal). The cost difference is material, and the time difference is the launch date: the custom route is 3 to 18 weeks longer, end to end, than the module route.
The other sources agree on the shape and disagree on the numbers, and the disagreement is worth stating plainly. MarkReady puts a pre-certified module product at $3,000–$10,000 and 3–6 weeks, a custom single-band radio at $8,000–$20,000 and 6–12 weeks, a multi-radio device at $15,000–$30,000 and 8–16 weeks, and a cellular device at $15,000–$40,000 and 8–16 weeks, and says using a pre-certified module typically cuts certification cost by 60–80% and halves the timeline.
Tovan puts a module-based product at $1,500–$10,000 and a custom radio at $8,000–$20,000+ and 6–12 weeks. Particle's own two pages disagree with each other: the guide puts the intentional radiator at $40,000 or more, the docs at $20,000–$30,000 over 4–8 weeks, and the unintentional radiator at about $3,000–$5,000 on one page and $1,000–$2,000 on the other. Hubble puts intentional radiator testing at $5,000–$30,000+, CE marking (RED, EMC, possibly LVD) at $10,000–$25,000+, and gives the planning rule: budget 15–20% of your total project budget for certification.
The spread is the answer, and the article uses Promise Legal's ranges as the primary and states the others as cross-checks, because the right number for a given radio and a given market is a lab quote, not a guide.
The TCB grant itself is the short pole. We couldn't confirm a published figure for the grant step on its own, so here is the one we could check, Particle's: the FCC application takes "around 8–12 weeks" generally, shrinking to "1–2 weeks" when a Telecommunication Certification Body accelerates it, and a pre-certified module shortens the certification timeline "from months to several days" because the host needs only the SDoC for Subpart B.
Lab testing and documentation are the long poles, not the review.
The real numbers: SparkFun's Artemis module
SparkFun's Artemis module is the real-world anchor, because SparkFun published the numbers. The Artemis is a BLE module built around the Ambiq Micro Apollo 3 (Cortex-M4F, BLE 5.0, 96 MHz, 1 MB flash), 10 mm by 15 mm, and SparkFun's post "Getting a Module FCC Certified" gives the quote from Unitato, the lab, line by line:
- FCC Part 15 Testing & Certification (FCC Part 15C: 15.212, 15.203, 15.205, 15.207, 15.209, 15.247, and 2.1093 for RF exposure): $4,000
- ISED Testing & Certification (RSS-247 Issue 2, RSSGen Issue 5, ICES 003): $3,000
- Canadian Agency Fee (one-time, with an annual renewal fee; Canada requires all non-Canadian companies to have a registered agent in Canada): $600
- CE Testing & Certification (CE RED: EN 300 328 v2.1.1, EN 301 489-1 v1.9.2 and -17 v3.2.0, EN 62479:2010): $2,800
- CE Testing & Certification (CE LVD: IEC 62368-1:2014): $1,800
The five line items sum to $12,200, the figure SparkFun gives for FCC/ISED/CE, including the $600 agency fee. Additional testing would be about $2,000 per model, and another $2,500–$6,000 in filing fees. The timeline: 1 June, the 50% down payment sent; 5 June, the carrier board and module received by the TCB; 10 July, testing completed and the draft report released, a five-week wait while the device was tested; 16 July, the application sent to the FCC; 16 August, 2ASW8-ART3MIS listed on the FCC, and a few days later 25186-ART3MIS listed on ISED.
Two and a half months, from down payment to listing. In a later interview, SparkFun's founder put it more simply: "less than $20k and took about seven weeks. I had to invest about a week's worth of time dealing with paperwork and documentation but much of it overlaps with the documentation our customers need anyway.
Luckily we passed first try." The module sells for $8.95 in single-unit quantities, and the $12,200 is the module maker's cost, amortised across every module they sell, which is why the module costs more per unit than the bare chip, and why the host's decision is not about the module's price.
The fine
The FCC's base forfeiture for marketing unauthorised radio frequency equipment is $7,000 per model, Table 1 to paragraph (b)(10) of 47 CFR §1.80, "Importation or marketing of unauthorized equipment, 7,000". The CoachComm Notice of Apparent Liability (DA 08-2042) is the worked example: CoachComm marketed one system, the same RF transmitter in both the wireless headsets and the command stations, and was apparently liable for $7,000. The HobbyKing case is the scale: the Bureau started with a base penalty of $7,000 for 65 models, a total of $455,000, and for the fifty models operated without equipment authorisation, adjusted each penalty by $5,250 for repeated and continuous violations, a proposed total of $2,861,128.
The ceiling is inflation-adjusted and updated periodically, and the sources give different figures for it: Promise Legal gives $19,246 per day and up to $144,344 for a single continuing violation, while the FCC's 2021 PIRATE Act order gives $20,731 per day and up to $155,485, the figures differ because they were inflation-adjusted at different dates, and the base $7,000 per model is consistent across all of them. For Example Labs' one model, the base is $7,000, and the fine is the cheap part.
The expensive part is the product that cannot be sold, the launch that does not happen, and the retest that takes six weeks.
The test plan before the lab
The test plan is written before the board is frozen, because the board is what the lab measures. The #19 piece is the EMC half of it: common-mode radiation accounts for 80–90% of emission failures, a 5 µA common-mode current at 300 MHz on a 1-metre cable exceeds FCC Class B, and split ground planes are the most common reason boards fail in the chamber, because a gap in the return path forces the return current to detour and the loop area expands.
A 4-layer board produces about 15 dB less radiation than a 2-layer board, and boards above 50 MHz needing FCC Class B or CE almost always need 4 layers. The limits the board has to meet, from #19: FCC Part 15 §15.109 Class B at 3 m, 30–88 MHz 100 µV/m, 88–216 MHz 150 µV/m, 216–960 MHz 200 µV/m, above 960 MHz 500 µV/m; CISPR 32 Class B at 3 m, 30–230 MHz 40 dBµV/m, 230–1,000 MHz 47 dBµV/m.
The #34 piece is the antenna half: the ground plane is the counterpoise, the keep-out is a copper-free zone on every layer beneath and around the radiating element, the module's antenna is the antenna the host must use, and the enclosure must not touch it, Espressif asks for at least 15 mm clearance to any metallic housing element, and the #35 piece's sealed box is the same warning from the thermal side.
The #5 piece is the board half: the copper, the vias, and the ground plane the heat and the return current both leave through. The #7 piece is the enclosure half: the box the antenna lives in, and the IP rating that is a laboratory test on a new unit for thirty minutes.
The documentation package, from §2.1033, is assembled before any lab work: a block diagram showing every oscillator, the signal path at each block, the tuning ranges, and the intermediate frequencies; for intentional radiators, a full schematic; a description of operation covering the ground system, the antenna configuration, and, for devices using digital modulation, the modulation system including the filter response and the modulating waveform; internal photographs at high enough resolution to show the exterior, the construction, the component placement, and the chassis assembly; and a statement confirming compliance with the applicable RF radiation exposure limits.
The RF exposure statement is the one founders forget: the module must comply with RF exposure requirements in the final configuration, and the exposure that was compliant on the module's test board may not be compliant in the host's enclosure, at the host's distance from the user.
And the label: the FCC ID must appear on the device, the compliance statement must appear with the product, and the module's FCC ID on the host is what tells the buyer, and the regulator, whose authorisation the radio is operating under.
DEMO
The Example Labs field sensor hub is the demo firm: a 100 × 60 × 40 mm unit, 4-layer board, BLE radio at 2.4 GHz, plastic enclosure from #7, and the antenna from #34. The arithmetic was run in Python before writing.
Step 1, the parts. The module route uses the ESP32-WROOM-32E from #34: 18 × 25.5 mm, on-board PCB antenna, $2.00–$3.50 at 10,000 units. The custom route uses the bare chip: $0.80–$1.50 plus passives. The module costs $0.50–$2.70 more per unit, with a midpoint of $1.60, and at 10,000 units, the module costs $16,000 more in parts (range $5,000–$27,000); at 5,000 units, $8,000 more; at 20,000 units, $32,000 more; at 50,000 units, $80,000 more.
Step 2, the certification. The module path narrows the obligation to Subpart B: $3,000–$8,000 and 2–6 weeks. The custom radio costs $18,000–$58,000 and 8–16 weeks for lab testing alone, with the full end-to-end timeline running 9–20 weeks. The custom route's certification premium is $10,000–$55,000 (midpoint $32,500), and it is 3 to 18 weeks longer, end to end.
Step 3, the break-even. The certification premium divided by the per-unit saving is the volume at which the custom route pays for itself. At the midpoint ($32,500 ÷ $1.60), the break-even is 20,312 units. At the low premium and high saving ($10,000 ÷ $2.70), it is 3,704 units; at the high premium and low saving ($55,000 ÷ $0.50), it is 110,000 units. The range is wide, and the midpoint is the number to plan on: for a founder shipping hundreds or a few thousand units, the module wins on cost alone, before the time is counted, and the custom route only wins at tens of thousands of units, where the per-unit saving finally overtakes the certification premium.
Step 4, the time, and what it costs. The module path is 2–6 weeks; the custom route is 9–20 weeks end to end. The difference is 3 to 18 weeks of launch delay, 3 to 18 weeks in which the product cannot be sold, the quarter's target cannot be closed, and the competitor's product is on the shelf. The SparkFun Artemis timeline is the real-world anchor for what a module certification costs the module maker: two and a half months, from down payment to listing, and about a week's worth of the founder's time on paperwork and documentation. The host using a pre-certified module does not pay that, it pays the Subpart B test, and it ships in weeks, not months.
Step 5, the conditions that evaporate the authorisation. The Example Labs hub uses the WROOM-32E's on-board PCB antenna, with the 15 mm housing clearance Espressif asks for, and the keep-out from #34. Change the antenna, a trace antenna instead of the module's, a different keep-out, a ground plane shrunk to fit a smaller board, and the module's grant no longer covers the host. Put the hub in a metal enclosure, and the antenna moves by more than 40 MHz and its return loss degrades from −15 dB to −6 dB, from #34. Raise the transmit power in firmware, and the conducted output exceeds the 1 W limit in 2400–2483.5 MHz. Each of those is a change in the design, circuitry, or construction under §2.932, and each of them needs a new application, except for a permissive change under §2.1043.
Step 6, the fine, and the test plan. For Example Labs' one model, the base forfeiture for marketing unauthorised equipment is $7,000, and the fine is the cheap part. The test plan for the hub is the module route: the WROOM-32E, its antenna, its keep-out, and its 15 mm housing clearance, preserved; the host's Subpart B test to the Class B limits (FCC 30–88 MHz 100 µV/m, 88–216 MHz 150 µV/m, 216–960 MHz 200 µV/m, above 960 MHz 500 µV/m at 3 m; CISPR 32 Class B 30–230 MHz 40 dBµV/m, 230–1,000 MHz 47 dBµV/m); the CE RED test plan, EMC to EN 55032 and EN 55035, safety to EN 62368-1, radio to EN 300 328, and the cybersecurity assessment to EN 18031, which has applied since 1 August 2025; the RF exposure statement in the final configuration; and the label with the module's FCC ID.
Step 7, the recommendation. The module route for the hub: the volumes are hundreds to a few thousand units, far below the ~20,000-unit break-even, and the launch is in weeks, not months. The custom route is the right decision at tens of thousands of units, when the per-unit saving finally overtakes the certification premium, and it is a decision to make with the lab quote in hand, not with the guide's range, because the spread between the sources is the answer.
The decision test: five questions
A hardware founder whose wireless product is ready to ship can answer five questions in an afternoon. If the answer to three of them is no, the product is not ready to ship, and the launch date is the retest date.
- Is the radio a module, or a custom design, and was that decided at the schematic? If the decision was never made, it was made by default, and the default is the custom radio, which costs $18,000–$58,000 and 8–16 weeks, against $3,000–$8,000 and 2–6 weeks for the module. The module's extra parts cost is $1.60 a unit at the midpoint; the custom route's extra certification cost is $32,500 at the midpoint. The break-even is roughly 20,000 units.
- Are the module's grant conditions preserved, the antenna, the keep-out, the ground plane, the enclosure? If the antenna was changed, the keep-out was shrunk, or the enclosure is metal, the module's authorisation has evaporated, and the host needs a new application. The antenna the module was tested with is the antenna the host must use, in the environment it was tested in.
- Has the host been tested under Subpart B? If the answer is "the module is certified, so we're covered," it is wrong: the module settles Subpart C, and the host's digital circuitry is an unintentional radiator under Subpart B that still needs its own authorisation. The host manufacturer is responsible for it.
- Is there a CE test plan, not just an FCC one? If the product is sold in the EU, the RED applies, radio to EN 300 328, EMC to EN 55032 and EN 55035, safety to EN 62368-1, and the cybersecurity assessment to EN 18031, which has applied since 1 August 2025. The FCC tests only what the device emits; the EU requires immunity and integrates safety.
- Is the documentation package assembled, and is the RF exposure statement in the final configuration? If the block diagram, the schematic, the description of operation, the internal photographs, and the RF exposure statement are not ready, the TCB has nothing to review, and the lab has nothing to test. The exposure that was compliant on the module's test board may not be compliant in the host's enclosure, at the host's distance from the user.
Objections
"We'll just use a pre-certified module and skip certification." The module is certified. The host is not. The module's grant covers the radio function, provided the tested conditions are preserved, and the host still needs Subpart B testing for its digital circuitry, its own labelling, and its own RF exposure compliance in the final configuration. The module path narrows the obligation to $3,000–$8,000 and 2–6 weeks. It does not remove it.
"Our product is a prototype, so the rules don't apply." The rules apply to marketing, advertising or selling in the US, and a prototype that is sold, or advertised for sale, is marketed. A prototype that is never sold and never advertised is not marketed, and the FCC's rules for prototype and evaluation boards are a different question, for the lab to answer. The launch date is the date the product is marketed, and the certification has to be in hand before it.
"We'll certify after we launch, the fine is only $7,000." The base forfeiture is $7,000 per model, and the HobbyKing case started at $455,000 for 65 models and ended at a proposed $2,861,128. But the fine is the cheap part: the product that cannot be sold, the launch that does not happen, the retest that takes six weeks, and the customers who bought the competitor's product in the meantime. The $7,000 is the price of the letter. The launch delay is the price of the decision.
"CE is just a sticker." CE marking is the manufacturer's own declaration, and the technical file is the evidence behind it, and the evidence is the test reports, the standards, and the Declaration of Conformity. A sticker without a file is a declaration without evidence, and the regulator's first question is always the file. The EU charges no fee for the mark itself, which is why the sticker is cheap and the file is not.
"We'll design the radio ourselves, it's cheaper per unit." It is cheaper per unit, by $1.60 at the midpoint, and it costs $32,500 more in certification at the midpoint, and 3 to 18 weeks longer. The break-even is roughly 20,000 units. Below that, the custom radio is the more expensive decision, and the launch delay is the more expensive part of it.
Sources
- 47 CFR §15.201 (eCFR), "(b) Except as otherwise exempted in paragraph (c) of this section and in § 15.23, all intentional radiators operating under the provisions of this part shall be certified by the Telecommunication Certification Bodies pursuant to the procedures in subpart J of part 2 of this chapter prior to marketing."
What we used
§15.201(a): carrier current systems, devices under §§15.211, 15.213, and 15.221, and devices below 490 kHz with all emissions at least 40 dB below the §15.209 limits are subject to SDoC instead
- 47 CFR §2.927 (eCFR), "A grant of certification recognizes the determination that the equipment has been shown to be capable of compliance with the applicable technical standards if no unauthorized change is made in the equipment and if the equipment is properly maintained and operated."
- 47 CFR §2.932 (eCFR), "A new application for an equipment authorization shall be filed whenever there is a change in the design, circuitry or construction of an equipment or device for which an equipment authorization has been issued, except as provided in paragraphs (b) through (d) of this section."
What we used
Permissive changes may be made under §2.1043
- CREAHIVE, "Radio Approvals for IoT: FCC, CE and UKCA" (checked 4 November 2026)
What we used
Section 15.201 says that, apart from listed exceptions, "all intentional radiators operating under the provisions of this part shall be certified by the Telecommunication Certification Bodies" before marketing; §15.212 defines a modular transmitter as "a completely self-contained radiofrequency transmitter device that is typically incorporated into another product"; a module approval does not automatically cover the finished product, the host must follow the module's grant conditions, including its antenna, and the rest of the product may have obligations of its own
- FedLaws, "Intentional Radiator: FCC Part 15 Testing, Certification, and Labeling"
What we used
The grant produces an FCC ID that must appear on the device, and the device must carry a specific compliance statement; §15.203: the device must be built so that no antenna other than the one supplied by the manufacturer can be used (permanently attached antenna or unique coupling mechanism); §15.19: the two conditions (must not cause harmful interference; must accept any interference received); §2.1033: the documentation package (block diagram, full schematic for intentional radiators, description of operation, internal photographs, RF exposure statement)
- Duobay, "FCC Part 15B vs 15C for a BLE Wearable"
What we used
§15.212: a single modular transmitter must have its own shielding, buffered modulation and data inputs, its own power supply regulation, and a permanently attached or unique-coupler antenna; tested stand-alone, carries its own FCC ID, comes with instructions for the host maker; RF exposure compliance must hold in the final configuration; §15.247: for a 2.4 GHz digital modulation radio, a 6 dB bandwidth of at least 500 kHz and a conducted output limit of 1 W in 2400–2483.5 MHz
- Laird/Ezurio, "FCC Guidance for Incorporating Transmitter Modules" (KDB 996369)
What we used
The eight single-module criteria; a limited modular approval restricts the implementation to a host or environment in which the module can satisfy all eight criteria; the host must satisfy all pertinent FCC regulations that do not relate to the module (e.g. FCC 15B for a computer system); if the FCC ID of the module is labelled on the host, additional authorisation is not needed outside of radiated emissions and RF exposure (SAR), as long as the conditions hold
- Promise Legal, "FCC Certification and CE Marking for Connected Devices"
What we used
A custom radio design certification typically runs $18,000–$58,000 and takes 8–16 weeks; the pre-certified module path narrows the obligation to Subpart B testing at $3,000–$8,000 and 2–6 weeks; the full end-to-end custom timeline runs 9–20 weeks; the FCC's base forfeiture for marketing unauthorised radio frequency equipment is $7,000 per model, with a statutory per-violation ceiling of $19,246 per day and up to $144,344 for a single continuing violation (inflation-adjusted, updated periodically)
- MarkReady, "FCC Certification Cost (2026)"
What we used
Simple digital device SDoC $1,500–$5,000, 2–4 weeks; IoT with a pre-certified module $3,000–$10,000, 3–6 weeks; custom single-band RF $8,000–$20,000, 6–12 weeks; multi-radio $15,000–$30,000, 8–16 weeks; cellular $15,000–$40,000, 8–16 weeks; smartphone $50,000–$200,000+, 6–9 months; using a pre-certified module typically cuts certification cost by 60–80% and halves the timeline; module + host testing breakdown (unintentional emissions $1,500–$3,000, TCB processing $500–$1,500, documentation $500–$1,000, total $2,500–$5,500)
- Tovan, "Do I Need FCC Certification for My Device?"
What we used
Radio with a pre-certified module $1,500–$10,000; custom radio $8,000–$20,000+ and 6–12 weeks; SDoC $600–$5,000 and 2–4 weeks
- Cimpleo, "FCC and CE Certification Cost for IoT Hardware"
What we used
Particle's guide puts the intentional radiator at $40,000 or more and the unintentional radiator at about $3,000–$5,000; Particle's docs put the intentional radiator at $20,000–$30,000 over 4–8 weeks and the unintentional radiator at $1,000–$2,000; Hubble puts intentional radiator testing at $5,000–$30,000+, CE marking (RED, EMC, possibly LVD) at $10,000–$25,000+, cellular carrier certification at $15,000–$50,000+ over 2–6 months; Hubble's planning rule: budget 15–20% of the total project budget for certification; Particle: the FCC application takes "around 8–12 weeks", shrinking to "1–2 weeks" when a TCB accelerates it, and a pre-certified module shortens the timeline "from months to several days" because the host needs only the SDoC for Subpart B
- SparkFun, "Getting a Module FCC Certified"
What we used
FCC Part 15C (15.212, 15.203, 15.205, 15.207, 15.209, 15.247, 2.1093 RF Exposure): $4,000; ISED (RSS-247 Issue 2, RSSGen Issue 5, ICES 003): $3,000; Canadian Agency Fee: $600; CE RED (EN 300 328 v2.1.1, EN 301 489-1 v1.9.2 and -17 v3.2.0, EN 62479:2010): $2,800; CE LVD (IEC 62368-1:2014): $1,800; the five line items sum to $12,200; additional testing ~$2,000 per model and another $2,500–$6,000 in filing fees; five weeks of testing; timeline 1 June down payment → 5 June received by the TCB → 10 July draft report → 16 July application sent → 16 August 2ASW8-ART3MIS listed on the FCC and 25186-ART3MIS listed on ISED; two and a half months total
- Hackster, "A Change of Direction for SparkFun?"
What we used
"less than $20k and took about seven weeks. I had to invest about a week's worth of time dealing with paperwork and documentation but much of it overlaps with the documentation our customers need anyway. Luckily we passed first try." The Artemis module sells for $8.95 in single-unit quantities
- FCC, Notice of Apparent Liability DA 08-2042 (CoachComm), "the base forfeiture amount for the marketing of unauthorized equipment is $7,000"
What we used
CoachComm apparently liable for $7,000 for marketing one system (the same RF transmitter in both the wireless headsets and the command stations)
- FCC, §1.80 Table 1 (2021 PIRATE Act order), "Importation or marketing of unauthorized equipment, 7,000"
What we used
Maximum forfeiture penalty for any case not previously covered: $20,731 per violation or per day, up to $155,485 for a single continuing violation
- Lexology, "FCC Proposes Maximum Penalties for 'Egregious' Marketing Recreational RF Devices" (HobbyKing, 2018)
What we used
The Bureau started with a base penalty of $7,000 for 65 models, a total of $455,000; for the fifty models operated without equipment authorisation, adjusted each penalty by $5,250 for repeated and continuous violations; proposed total $2,861,128
- MarkReady, "FCC vs CE vs ISED: Certification Requirements Compared"
What we used
CE marking is a manufacturer's self-declaration; no government agency issues the CE mark; RED 2014/53/EU bundles EMC, safety, radio performance, and (since August 2025) cybersecurity into one framework; the FCC tests only what the device emits (no immunity, no safety, UL/NRTL is separate); the EU requires immunity (IEC 61000-4-x) and integrates safety via the LVD; cybersecurity required since August 2025 (RED Art. 3.3, EN 18031); EMC standard EN 55032 (emissions) + EN 55035 (immunity); Wi-Fi/BT standard EN 300 328, EN 301 893; typical total cost FCC $5,000–$15,000, CE/RED $8,000–$25,000; timelines FCC 3–6 weeks, CE/RED 4–12 weeks
- BreezeHW, "Cert Navigator"
What we used
FCC typical $5,000, range $3,000–$10,000, 4–8 weeks; CE/RED typical $6,000, range $3,000–$12,000, 6–10 weeks; UL/IEC 62368 typical $10,000, range $5,000–$20,000, 8–14 weeks; ISED typical $4,000, range $2,000–$8,000, 4–6 weeks
- Example Labs figures from the cluster: the ESP32-WROOM-32E module (18 × 25.5 mm, on-board PCB antenna
What we used
$2.00–$3.50 at 10,000 units) vs the bare chip ($0.80–$1.50 plus passives) and full bare-chip certification ~$5,000–$15,000+ (#34); the ground plane as the counterpoise, the keep-out on every layer, the 15 mm Espressif housing clearance, and the metal enclosure moving a printed antenna by more than 40 MHz (#34); the Class B limits at 3 m (FCC 30–88 MHz 100 µV/m, 88–216 MHz 150 µV/m, 216–960 MHz 200 µV/m, above 960 MHz 500 µV/m; CISPR 32 Class B 30–230 MHz 40 dBµV/m, 230–1,000 MHz 47 dBµV/m) and common-mode radiation accounting for 80–90% of emission failures (#19); the sealed 100 × 60 × 40 mm box with 5 W inside running 25 °C hotter than the air around it (#7); the RED cybersecurity assessment (EN 18031, since 1 August 2025, Delegated Regulation (EU) 2022/30, RED Art 3(3)(d)(e)(f)) and the Machinery Regulation deadline (20 January 2027) (#15)